Recipe for PD Roaming

From CDGWiki

Jump to: navigation, search

[edit] Recipe for Packet Data Roaming

  • There is a lot of practical experience w/ PD roaming
  • Need for “recipe” for PD roaming
  • Many supporting informational documents
  • New operators asking “What do I do?”
  • Provide steps and timelines
  • This work will be captured in future reference document

[edit] Tampa Meeting Brainstorming

  • Get network ready: evaluate status; look @ min. requirements document #147;
  • BGP side – (1) multiple ANSs (which?), (2) consultants – no ASN – just a T1 to ISP – no BGP AS
  • Strongly recommend talking to CRX prior to roaming partners
  • Look at billing development as early as possible
  • Recommend reviewing #147: everything worded appropriately?
  • Different requirements mean different implementations; operators have different requirement
  • Understanding timers important (state dependent)
  • Manage organizational requirements early; aligning resources difficult
  • Don’t overstate your capabilities; don’t lose credibility over concern over losing roaming partner
  • Resource challenges are more difficult in small operators
  • Meet with your CRM early (carrier relations manager)-first step!
  • Need to understand process and expected timelines
  • Inbound vs. outbound? Decide a strategy
  • Establish CRX – project manager w/ CRX; project management document;

W/ operator – working w/ engineering and not project management; don’t get estimates on deliverable;

  • Any operators : Observe standards!!!
  • Devices ready?: Devices need to be ready to roam; may not be straightforward; early device testing;
  • Need to evaluate products/applications while roaming
  • Voice available? “Tough” if not there for 1x;
  • Adding EV-DO to 1x data more straightforward; device component challenging; requires a new project – surprised by device responses
  • Determine what is served: SIP, L2TP, MIP? Devices?
  • Steps:
  • Preparation : exchange TDS, discuss, etc.
  • Base architecture (multiple roaming)
  • CRX survey (exchanging BGP info, etc.) – delay on hardward
  • CRX connectivity (2 weeks – 6 months)
  • AAA connectivity via CRX (1 day – 3 months)
  • Incompatible attributes can slow things down
  • PRL development (2 weeks – 3 months)
  • Session timers: timeouts
  • Revenue assurance test (moving forward: see revenue flow; can speed things up) : need to sign off on this